Construction moves forward on Holladay Boulevard

Questar is continuing to work on lowering their gas line along the east side of the south end of Holladay Boulevard. Their work should be complete early in the week, after which Harper will be working on subgrade preparation for curb and gutter. Underground storm drains, capping of quest utility lines and grading work will be done on the east end of Murray-Holladay Road. Asphalt paving is scheduled for the west end of Murray Holladay Road. Curb and gutter will be poured on the north end of Holladay Boulevard and sections of concrete pavement will be placed during the week. Hunt Electric will continue to place street light bases in a variety of locations throughout the project area.